Time Schedule

5 hours - Sub floor framing and sizolation paper
6 hours - Wall framing x4 Two Longitude & Two Racking
7 hours - installing Gib board to wall frame
7 hours - Roof framing and Timber Purlins
10 hours - Building Paper, Building wrap, Cavity batterns of exterior walls
5 hours - installing x2 windows and x1 rancheslider including window tape and flashing's
3 hours - Finishing Lines, skirting